PhaseName of the workProgress details
01Foundation workFoundation 100% completed, Basement 2 100% completed, Basement 1 Roof slab 100% completed.
02Super structure work100% Completed.
03Block work90% Completed.
04Electrical conducting work80% Completed.
05Wall tiles workPending
06Common sanitary & Plumbing line work70% Completed.
07Outside plastering workPending
08Floor tiles/Marble workPending
09L.C.C workPending
10Grill & railing work90% Completed.
11Inside paint & polishing workPending
12Switch/socket fitting workPending