PhaseName of the workProgress details
01Foundation workFoundation 100% completed, Basement 2 100% completed, Basement 1 Roof slab 100% completed.
02Super structure work8% completed. Ground floor roof slab casting completed.
03Block workPending
04Electrical conduiting workPending
05Wall tiles workPending
06Common sanitary & Plumbing line workPending
07Outside plastering workPending
08Floor tiles/Marble workPending
09L.C.C workPending
10Grill & railing workPending
11Inside paint & polishing workPending
12Switch/socket fitting workPending